Where are vacant units getting stuck between residents?
Put actual dates on the turn from move-out to the next move-in. Identify the first milestone without evidence or an accountable person. Measure time spent getting the unit ready separately from time spent marketing a ready unit.
Record the date and the evidence at each milestone
Start with one unit or group a larger set by blocker. Use the same milestone definitions across vendors and buildings so a delayed inspection and a slow leasing response stay visible as different problems.
| Milestone | Evidence | Who clears the blocker |
|---|---|---|
| Move-out and access | Confirmed possession and access at the unit | Manager confirms access and schedules the inspection. |
| Scope and approvals | Walkthrough, quoted work and approval record | Manager routes the decision to the authorized approver. |
| Work finished | Vendor update and condition evidence tied to the work order | Manager follows up on incomplete work or missing proof. |
| Readiness verified | Dated walkthrough covering blockers and access | Assigned reviewer confirms the unit can be offered as ready. |
| Listed, leased and occupied | Listing date, signed start date and actual move-in | Leasing owner checks showing activity and remaining delays. |
Use the dates to assign the next action
Fictional example: a resident leaves on the 1st, work is reported complete on the 5th, readiness is verified on the 8th, and the unit is listed on the 10th. The next resident moves in on the 18th. Ask who can shorten the three days between work completion and verification and the two days between verification and listing. Track the eight days from listing to move-in separately.
If a required check is missing, keep the readiness decision open and give the reviewer a next date. A vendor completion message supports follow-up. The walkthrough supports the readiness decision.